Geothermal Breakthrough in South Texas Signals New Era for ERCOT
Sonal Patel | Source: Power | Posted 09/03/2025

In just 12 months, Sage Geosystems and San Miguel Electric Cooperative built the world’s first pressure geothermal system. It is now poised to deliver long-duration, dispatchable storage for the Electric Reliability Council of Texas (ERCOT) as variable generation and data center demand surge.
AI generated summary
Sage Geosystems and San Miguel Electric Cooperative have achieved a significant milestone by developing the world's first pressure geothermal system in South Texas. This innovative project aims to provide long-duration, dispatchable energy storage for the Electric Reliability Council of Texas (ERCOT) amidst increasing demand from variable energy sources and data centers. The geothermal pilot, known as SMECI Well #1, was completed in just 12 months, showcasing a new model for energy storage that leverages existing oilfield expertise and advanced technology.
The pressure geothermal system operates similarly to pumped-storage hydropower but utilizes underground reservoirs to store and release energy. With a projected round-trip efficiency of 70-75%, it offers a competitive alternative to lithium-ion batteries for longer discharge durations, while minimizing water loss and avoiding the environmental challenges associated with battery production. As the project prepares for grid interconnection in December 2025, Sage Geosystems plans to expand its geothermal initiatives, focusing on energy storage and power generation to meet the growing energy demands of data centers and other sectors.
Link to Original Article
Please find the link to the full article below. (Please note that content provider might require a paid subscription)
Source Link: https://www.powermag.com/geothermal-breakthrough-in-south-texas-signals-new-era-for-ercot/
09/05 - 9:00 AM
ERCOT - WMWG Meeting - Webex Only09/08 - 9:30 AM
ERCOT - RTCB Market Trials Weekly Webex09/08 - 10:00 AM
PUCT - Comments Due Project No. 5848409/09 - 3:00 PM
09/04/2025
09/04/2025 RTCBTF/TWG Workshop #3 – Detailed Discussion of RTC+B Closed Loop LFC Testing for September09/04/2025
How modernized energy forecasting can make grid operations more efficient09/04/2025
Texas Trounces California in Energy Production—But the Policy Gap Is Closing09/04/2025
Texas REP Urges PUC To Allow Use Of Demand Response, DERs For Proposed Generation Firming Requirements09/04/2025
Public Utility Commission of Texas celebrates 50 years of serving TexansCY 2025 RETAIL PERFORMANCE MEASURE REPORTS PURSUANT TO 16 TAC 25.88 - (123 filings)
CY 2024 RETAIL ELECTRIC PROVIDER (REP) ANNUAL REPORTS AND CY 2025 REP SEMI-ANNUAL REPORTS PURSUANT TO 16 TAC 25.107(I) - (106 filings)
APPLICATION OF ONCOR ELECTRIC DELIVERY COMPANY LLC FOR AUTHORITY TO CHANGE RATES - (91 filings)
APPLICATION OF EL PASO ELECTRIC COMPANY FOR AUTHORITY TO CHANGE RATES - (87 filings)
BROKER REGISTRATIONS - (68 filings)
APPLICATION OF ENTERGY TEXAS, INC. TO AMEND ITS CERTIFICATE OF CONVENIENCE AND NECESSITY FOR THE CYPRESS-TO-LEGEND 500-KV TRANSMISSION LINE IN HARDIN AND JEFFERSON COUNTIES - (56 filings)
AGGREGATOR ANNUAL REPORTS - (44 filings)