ERCOT Working To Use CenterPoint-TDU Mobile Generation As Alternative To RMRs for Two CPS Units; Will Recommend RMR Agreement For One CPS Unit

Paul Ring | Source: Energy Choice Matters | Posted 11/25/2024

Keyword Tags:

ERCOT reported at today's Texas PUC opening meeting that it is working on developing an agreement to move the mobile generation units of CenterPoint Energy Houston Electric from Houston to the San Antonio area, as an alternative to entering into reliability must-run agreements with two CPS Energy units which will suspend operations


AI generated summary

ERCOT is actively working on an agreement to relocate the mobile generation units of CenterPoint Energy Houston Electric from Houston to the San Antonio area as an alternative to initiating reliability must-run agreements with two CPS Energy units that are set to suspend operations. This shift would involve addressing feasibility, regulatory, and cost considerations.

The mobile generation capacity of approximately 500 MW from CenterPoint Energy Houston Electric matches the combined capacity of the two aging CPS Energy Braunig units that are slated for suspension, Units 1 & 2. ERCOT is temporarily setting aside the need for a reliability must-run agreement for Units 1 & 2 to focus on exploring the potential use of mobile generation from CEHE, with discussions ongoing with relevant parties to evaluate technical and cost aspects of this proposed solution.



Link to Original Article

Please find the link to the full article below. (Please note that content provider might require a paid subscription)


Source Link: http://www.energychoicematters.com/stories/20241121e.html

Create a free trial account: Sign Up

Grid monitor is free to try. No credit card required


Already have an account? Login

Most Active PUCT Filings

APPLICATION OF ENTERGY TEXAS, INC. TO AMEND ITS CERTIFICATE OF CONVENIENCE AND NECESSITY FOR THE SETEX AREA RELIABILITY PROJECT IN JASPER, MONTGOMERY, NEWTON, POLK, SAN JACINTO, TRINITY, TYLER, AND WALKER COUNTIES - (287 filings)

APPLICATION OF CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC FOR APPROVAL OF ITS 2026-2028 TRANSMISSION AND DISTRIBUTION SYSTEM RESILIENCY PLAN - (89 filings)

APPLICATION OF EL PASO ELECTRIC COMPANY FOR AUTHORITY TO CHANGE RATES - (75 filings)

CY 2024 ANNUAL POWER LINE INSPECTION & SAFETY REPORT IN PURSUANT TO 16 TAC § 25.97(F) - (70 filings)

BROKER REGISTRATIONS - (69 filings)

APPLICATION OF ENTERGY TEXAS, INC. TO AMEND ITS CERTIFICATE OF CONVENIENCE AND NECESSITY TO CONSTRUCT A PORTFOLIO OF DISPATCHABLE GENERATION RESOURCES - (57 filings)

APPLICATION OF CROSS TEXAS TRANSMISSION, LLC FOR AUTHORITY TO CHANGE RATES AND TARIFFS - (53 filings)