Meeting Summary - 08/20/24 Board of Directors Meeting
Grid Monitor AI
08/21/2024
<p><span style="font-weight: 400;">1 - Call General Session to Order - Vice Chair - Bill Flores</span></p>
<p><span style="font-weight: 400;">2 - Notice of Public Comment, if Any Discussion - Vice Chair - Bill Flores</span></p>
<ul>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">No Public Comment</span></li>
</ul>
<p><a href="/sharing/?token=79450376-a1e6-49a8-baa3-2f2249f78da4"><span style="font-weight: 400;">3</span></a><span style="font-weight: 400;"> - Consent Agenda Vote - Vice Chair - Chad V. Seely</span></p>
<ul>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">NPRR1215 was removed from the consent agenda and will be discussed under agenda item 7.1.2.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">The TAC report includes revision requests unanimously recommended for approval and selected for additional discussion.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">The board approved the consent agenda with the exception of NPRR1215.</span></li>
</ul>
<p><a href="/sharing/?token=92554a1e-7f7d-47e0-8306-36c8d77e53c2"><span style="font-weight: 400;">3.1.1</span></a><span style="font-weight: 400;"> - NPRR1216, Implementation of Emergency Pricing Program - Vote - Chad V. Seely</span></p>
<ul>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">NPRR1216 addresses the implementation of the emergency price program as a result of a PUC rulemaking (Project 54585)</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">The program has a budget impact ranging from $175,000 to $225,000.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Implementation will occur in two phases.</span></li>
</ul>
<p><a href="/sharing/?token=3f8c4dcc-3d10-4516-878a-ae947f8d3100"><span style="font-weight: 400;">3.1.2</span></a><span style="font-weight: 400;"> - NPRR1217, Remove Verbal Dispatch Instruction VDI Requirement for Deployment and Recall of Load Resources and Emergency Response Service ERS Resources - Vote - Chad V. Seely</span></p>
<ul>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Budget impact between $10,000 to $20,000.</span></li>
</ul>
<p><a href="/sharing/?token=fd265e5d-8dfd-46bd-aeeb-3ff6325cdbd0"><span style="font-weight: 400;">4</span></a><span style="font-weight: 400;"> - June 18, 2024 General Session Meeting Minutes - Vote - Vice Chair - Bill Flores</span></p>
<ul>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Motion to approve June 18, 2024 meeting minutes passed.</span></li>
</ul>
<p><a href="/sharing/?token=2d8dc9ac-99c9-45bc-8670-88dc9792ba97"><span style="font-weight: 400;">5</span></a><span style="font-weight: 400;"> - CEO Update Discussion - Pablo Vegas</span></p>
<ul>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Pablo Vegas provided the </span><a href="https://ercot-control-docs.s3.us-west-2.amazonaws.com/16/5-ceo-update-revised.pdf"><span style="font-weight: 400;">CEO update</span></a><span style="font-weight: 400;">.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Upcoming market design analysis focusing on reliability, resiliency, and efficiency of the ERCOT market.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Current state of mitigations for the new South Texas interconnection reliability operating limit established in March.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Update on the progress related to the Permian Reliability plan and considerations for the larger 2024 regional transmission plan.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Operational highlights: Aug 20 operation is likely one of the peak days this summer with significant differences from last summer's weather and resource mix.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Increase in energy storage, solar, and wind resources contributing to less scarcity conditions.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Future market design framework discussed to provide context for market features and services.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Framework to evaluate ERCOT market design qualitatively and quantitatively includes 7 attributes, slide 4 of the update.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">New South Texas IROL update: additional transfer capabilities projects endorsed by ERCOT board, expected completion between 2027-2029.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Permian Basin reliability plan filed with the PUC as per 88R-HB5066, with a projected load of 23,700 MW by 2030.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Development of the 2024 regional transmission plan to address forecasted load growth including high voltage transmission lines options.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Discussion on the timeline for 765 kV vs. 345 kV transmission projects and supply chain considerations.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">ERCOT’s planning and coordination with stakeholders and transmission developers emphasized to address evolving needs and supply chain timelines.</span></li>
</ul>
<p><a href="/sharing/?token=df698a14-6241-409e-b543-feeda7fe43ad"><span style="font-weight: 400;">5.1</span></a><span style="font-weight: 400;"> - Update on CPS Energy Reliability Must-Run RMR and Must-Run Alternative MRA Process Discussion - Pablo Vegas / Woody Rickerson / Chad V.Seely</span></p>
<ul>
<li style="font-weight: 400;" aria-level="1"><a href="https://ercot-control-docs.s3.us-west-2.amazonaws.com/16/5-1-update-on-cps-energy-reliability-must-run-rmr-and-must-run-alternative-mra-process.pdf"><span style="font-weight: 400;">Update</span></a><span style="font-weight: 400;"> on CPS Energy RMR and MRA process.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Background and context of the Braunig units operated by CPS in San Antonio undergoing RMR evaluation due to proposed suspension of operations.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Issues unique to this situation related to early repair and continued operations during winter/summer seasons.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Trigger of reliability analysis under PUC rules finding deficiencies in ERCOT system due to suspension.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Explanation of the RMR analysis methodology focusing on transmission reliability rather than capacity.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Considerations for temporary fixes like new transmission lines or units until proper mitigation is in place.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Two-year necessity of the CPS units until CPS transmission projects come online in summer of 2027.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Current RFP for must-run alternatives is open and timeline extended to allow more industry response.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Board has to decide by December whether to go with RMR or alternatives based on risk assessment and reliability analysis.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Ongoing coordination with CPS regarding maintenance schedules and inspection of units before April 1, 2025.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Possible outage of one of the units (412 MW unit) for inspection to understand issues before RMR commences.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Consideration of lost opportunity costs if units are taken out for inspection early.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">ERCOT staff proposed to take an outage for inspection, working with CPS for detailed framework and timeline.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Addressing the challenge of methodology for calculating lost opportunity costs.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Importance of evaluating risk and operational characteristics for financial assessments to be fair for Texas consumers.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Examining if current MRA framework offers proper economic incentives, potential needs to revisit RMR framework for future situations.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">ERCOT will continue to negotiate and draft agreements ensuring fairness and clear communication with CPS.</span></li>
</ul>
<p><a href="/sharing/?token=5caaf4d0-57e2-415c-82a2-7f7f6672a209"><span style="font-weight: 400;">6</span></a><span style="font-weight: 400;"> - Board Education – Thermal Generation Development in ERCOT Discussion - Dave Maggio</span></p>
<ul>
<li style="font-weight: 400;" aria-level="1"><a href="https://ercot-control-docs.s3.us-west-2.amazonaws.com/15/6-board-education-thermal-generation-development-in-ercot-revised.pdf"><span style="font-weight: 400;">Introduction</span></a><span style="font-weight: 400;"> by Dave Maggio on the focus of the discussion: incentives for generation development, specifically thermal resources.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Incremental increase in gas technologies in the ERCOT market, with a continued focus on renewables and storage.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Discussion on factors impacting the outlook for generation development, including both improvements and impairments.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Comparative cost analysis across different technologies shared, mentioning the levelized cost of energy (LCOE) provided by Lazard.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Timeline of project development discussed, highlighting the median duration of around two years for the interconnection agreement process.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Emphasis on the importance of a reliability standard and updates on ERCOT's work with the PUC.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Highlighting load growth and its implications for generation development.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Discussion on impairments to outlook, such as EPA rules and cost of new entry (CONE).</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Comparison of historical Peaker Net Margin (PNM) to current CONE to gauge investment signals.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Future-focused approach on market design evaluation, especially considering a comprehensive framework for evaluating grid needs and market incentives.</span></li>
</ul>
<p><a href="/sharing/?token=818233bd-e634-4297-b913-457f966ef8d5"><span style="font-weight: 400;">7</span></a><span style="font-weight: 400;"> - TAC Report - Discussion - TAC Chair - Caitlin Smith</span></p>
<ul>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Caitlin Smith provided the TAC </span><a href="https://ercot-control-docs.s3.us-west-2.amazonaws.com/13/7-tac-report.pdf"><span style="font-weight: 400;">report</span></a><span style="font-weight: 400;">.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Voted unanimously to recommend approval of ten revision requests.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Three of the ten revision requests had opposing votes and were discussed further.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Endorsed the Oncor Temple Area Regional Planning group project (Option Five).</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Initiated discussions with stakeholders on the 2025 ancillary services methodology.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Plan to vote on the ancillary services methodology in September to present it to the board in October.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Workshop planned after August TAC meeting, concerning the ancillary services study from the 87th legislative session (87R-SB3)</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Discussing stakeholder process improvements to enhance transparency.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Upcoming workshop planned for September 5.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">NOGRR245 item not previously in front of TAC, with updates provided by ERCOT.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Focus on key issues for NOGRR245 with possible feedback and consensus needed by February.</span></li>
</ul>
<p><span style="font-weight: 400;">7.1 - Non-Unanimous and Other Selected Revision Requests Recommended by TAC for Approval - Vote - Vice Chair</span></p>
<p><a href="/sharing/?token=280f299d-283e-4384-9785-9d81a69f9480"><span style="font-weight: 400;">7.1.1</span></a><span style="font-weight: 400;"> - NPRR1190, High Dispatch Limit Override Provision for Increased Load Serving Entity Costs - Vote - Vice Chair - Caitlin Smith</span></p>
<ul>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">NPRR1190 focuses on high dispatch limit overrides for increased load serving entity costs.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Adds provision for recovery of financial loss from manual high dispatch limit overrides aimed at reducing real power output for QSC load obligation.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Current protocol allows compensation for day-ahead market obligations and affected bilateral contracts.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">NOEs struggle to recover costs due to self-arrangement obligations.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">NPRR1190 aims to address this issue.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">TAC approved NPRR1190 on June 24.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Six opposing votes from the consumer segment and one abstention from the independent retailer segment.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Opposers argue it contradicts nodal market design and might reward over-scheduling of undeliverable power, counter to energy-only market incentives.</span></li>
</ul>
<p><a href="/sharing/?token=21304d88-3560-4297-bdd6-f19880a26d60"><span style="font-weight: 400;">7.1.2</span></a><span style="font-weight: 400;"> - NPRR1215, Clarifications to the Day-Ahead Market DAM Energy-Only Offer Calculation Vote - Vice Chair - Caitlin Smith</span></p>
<ul>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">NPRR1215 relates to clarification of the Day-Ahead Market (DAM) energy-only offer calculation.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">The proposal was unanimously approved at the June TAC meeting.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">ERCOT filed comments on August 1 to correct a formula error.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">ERCOT discussed this plan at the July TAC meeting and outlined their intention to file comments and address any concerns.</span></li>
</ul>
<p><a href="/sharing/?token=50f1ac9d-c98d-4c8e-9e54-cd4ec7bbfbd1"><span style="font-weight: 400;">7.1.3</span></a><span style="font-weight: 400;"> - NPRR1219, Methodology Revisions and New Definitions for the Report on Capacity, Demand and Reserves in the ERCOT Region CDR – URGENT - Vote - Vice Chair - Caitlin Smith</span></p>
<ul>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Discussed NPRR1219 methodology revisions and new definitions for the Capacity, Demand, and Reserves (CDR) report.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Changes include revised methodologies for preparing the CDR and updated release schedules.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">A significant change requires switchable generation resource owners to provide information on unavailable switchable units for all seasons, not just summer and winter.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Part of ongoing reform efforts on CDR since Winter Storm Uri.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Alignment with Public Utility Commission discussions and previous market participant inputs, specifically the switch to the ELCC methodology.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Two opposing votes from the consumer segment and four abstentions from the consumer, independent generator, and independent power marketer segments.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Opposition due to the complexity of ELCCs and related policy issues connected to the reliability standard process at the Public Utility Commission.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Urgency noted for applying changes to the December CDR.</span></li>
</ul>
<p><a href="/sharing/?token=bee4e466-9e85-4f01-b182-8b60d90b8a19"><span style="font-weight: 400;">7.1.4</span></a><span style="font-weight: 400;"> - NPRR1230, Methodology for Setting Transmission Shadow Price Caps for an IROL in SCED – URGENT - Vote - Vice Chair - Caitlin Smith</span></p>
<ul>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Establishes shadow price cap for congestion impacting an IROL.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Enables ERCOT to manage power flows using existing operational and market tools instead of manual intervention.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Manual intervention introduces operational risk during periods of system stress.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Referenced an issue on September 6 2023 during the EEA event.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Two opposing votes from cooperative and municipal segments.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Four abstentions from cooperative and independent retail provider segments.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Opposition due to higher costs in ERCOT's analysis compared to the current manual solution.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Other opposing votes cited increased cost to specific load zones.</span></li>
</ul>
<p><a href="/sharing/?token=c9b8c826-564a-4d3e-b480-1275325abe14"><span style="font-weight: 400;">7.2</span></a><span style="font-weight: 400;"> - Reliability and Markets R&M Committee Recommendations on Non-Unanimous and Other Selected Revision Requests - Discussion - R&M Chair - Bob Flexen</span></p>
<ul>
<li style="font-weight: 400;" aria-level="1"><strong>NPRR1215:</strong><span style="font-weight: 400;"> TAC unanimously recommended NPRR1215 for approval. However, it was selected for further consideration due to an incorrect credit formula. The board moved to remand NPRR1215 back to TAC to correct the issue. Motion carried.</span></li>
<li style="font-weight: 400;" aria-level="1"><strong>NPRR1190:</strong><span style="font-weight: 400;"> The committee considered ERCOT comments and six opposing votes at TAC by consumers. It was recommended that more time was needed to analyze quantitative data before the October board meeting. The board moved to table NPRR1190. Motion carried.</span></li>
<li style="font-weight: 400;" aria-level="1"><strong>NPRR1219 and NPRR1230:</strong><span style="font-weight: 400;"> Both revision requests were considered alongside the TAC report and ERCOT comments. The R&M committee unanimously recommended approval of NPRR1219 and NPRR1230. The board moved to approve both requests. Motion carried.</span></li>
</ul>
<p><a href="/sharing/?token=a3e964e2-232c-42cc-867c-6f9f737c6e82"><span style="font-weight: 400;">8</span></a><span style="font-weight: 400;"> - Acceptance of 2023 ERCOT 401(k) Savings Plan Audit Report Vote - Vice Chair - Bill Flores</span></p>
<ul>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Finance and Audit Committee recommended board acceptance of the 2023 audit </span><a href="https://ercot-control-docs.s3.us-west-2.amazonaws.com/13/8-1-acceptance-of-2023-ercot-401-k-savings-plan-audit-report.pdf"><span style="font-weight: 400;">report </span></a><span style="font-weight: 400;">for the 401(k) savings plan.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">The audit report showed no material issues with plan administration.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">The 401(k) plan has approximately $390 million in assets, indicating significant growth from last year.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Auditors provided a clean opinion.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Board unanimously approved the audited financial statements of ERCOT's 401(k) savings plan as of December 31, 2023.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Reviewed standard committee briefs on financial performance, investment, and debt compliance; all reports were nominal except for one instance where investments were slightly over 10%.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Board reviewed the PUC ordered operating budget reconciliation for calendar year 2024; ERCOT plans to file materials with the commission before the September 1 deadline.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Next scheduled meeting in October to include the committee's annual self-evaluation and first draft of the 2025 internal audit plan.</span></li>
</ul>
<p><a href="/sharing/?token=72063433-1e23-4d59-99e2-ff2e1dadf043"><span style="font-weight: 400;">9</span></a><span style="font-weight: 400;"> - Ratification of Officer Vote - Vice Chair - Peggy Heeg</span></p>
<ul>
<li style="font-weight: 400;" aria-level="1"><a href="https://ercot-control-docs.s3.us-west-2.amazonaws.com/13/9-1-ratification-of-officer.pdf"><span style="font-weight: 400;">Ratification of Officer</span></a><span style="font-weight: 400;">.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Short general session, human resources, and Governance committee meeting held.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Committee recommended ratification of Gilbert Hughes as VP of public affairs of ERCOT effective July 2, 2024.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Upcoming meetings will cover year-end items such as compensation and succession planning.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Motion approved unanimously with no opposition or abstentions.</span></li>
</ul>
<p><span style="font-weight: 400;">10 - Reliability and Markets R&M Committee Report Discussion - R&M Chair - Bob Flexen</span></p>
<p><a href="/sharing/?token=4bf51167-3c84-49e8-8491-2b0560d96183"><span style="font-weight: 400;">10.1</span></a><span style="font-weight: 400;"> - NOGRR245, Inverter-Based Resource IBR Ride-Through Requirements – URGENT Vote - Vice Chair - Bob Flexen</span></p>
<ul>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">TAC recommended approval of NOGRR245 in June.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">The board tabled NOGRR245 for further development of consensus among ERCOT staff and certain stakeholders.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Joint commenters previously concerned with the NOGRR filed subsequent comments with no objections after ERCOT comments.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Motion to recommend approval of NOGRR245 as recommended by TAC in the 06/07/24 TAC report as amended by 08/16/24 ERCOT comments with a priority of 2025 and rank of 3515 and to designate a subsequent NOGRR as a board priority revision request to address the reaming details of the exemption process. </span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Motion approved unanimously.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Commissioner Jimmy Glotfelty suggested the ERCOT board get updates on NERC's IBR rule for mandatory reliability standards.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Chairman Gleeson made a comment on the need for broader discussions on policy decisions between ERCOT and PUC, noting some policy discussions might be more suitable for commission rulemaking rather than through ERCOT.</span></li>
</ul>
<p><a href="/sharing/?token=6671e5d7-d01e-4cb5-b6b4-c0bb519ec429"><span style="font-weight: 400;">10.2</span></a><span style="font-weight: 400;"> - Oncor Temple Area Regional Planning Group RPG Project Vote - Vice Chair - Bob Flexen</span></p>
<ul>
<li style="font-weight: 400;" aria-level="1"><strong>Project Details:</strong></li>
<ul>
<li style="font-weight: 400;" aria-level="2"><span style="font-weight: 400;">Cost: $272.6 million, Tier 1 project.</span></li>
<li style="font-weight: 400;" aria-level="2"><span style="font-weight: 400;">Expected Service Date: December 2028</span></li>
<li style="font-weight: 400;" aria-level="2"><span style="font-weight: 400;">Purpose: Address thermal overloads on transmission lines and transformers, as well as voltage violations in Bell county.</span></li>
</ul>
<li style="font-weight: 400;" aria-level="1"><strong>Planning Criteria:</strong><span style="font-weight: 400;"> Meet NERC and ERCOT reliability planning criteria</span></li>
<li style="font-weight: 400;" aria-level="1"><strong>Option Choice:</strong><span style="font-weight: 400;"> Option five A</span></li>
<li style="font-weight: 400;" aria-level="1"><strong>Justification for Option:</strong></li>
<ul>
<li style="font-weight: 400;" aria-level="2"><span style="font-weight: 400;">Least cost option</span></li>
<li style="font-weight: 400;" aria-level="2"><span style="font-weight: 400;">Meets planning criteria</span></li>
<li style="font-weight: 400;" aria-level="2"><span style="font-weight: 400;">Improves long-term load serving capability for future load growth</span></li>
<li style="font-weight: 400;" aria-level="2"><span style="font-weight: 400;">Requires least amount of needed CCN miles.</span></li>
</ul>
<li style="font-weight: 400;" aria-level="1"><strong>Motion Details:</strong></li>
<ul>
<li style="font-weight: 400;" aria-level="2"><span style="font-weight: 400;">Motion to endorse, as recommended by the R&M committee, the need for the tier 1 Oncor Temple area RPG project, Option five A, which ERCOT staff has independently reviewed and which TAC has voted unanimously to endorse based on NERC and ERCOT reliability planning criteria.</span></li>
<li style="font-weight: 400;" aria-level="2"><span style="font-weight: 400;">Motion carries unanimously.</span></li>
</ul>
</ul>
<p><a href="/sharing/?token=e39261dd-b3a0-46c2-a785-3723798f0d68"><span style="font-weight: 400;">11</span></a><span style="font-weight: 400;"> - Technology and Security T&S Committee Report Discussion - T&S Chair - John Swanson</span></p>
<h5><a href="https://ercot-control-docs.s3.us-west-2.amazonaws.com/12/4-introduction-to-grid-enhancing-technologies-gets-.pdf"><strong>Presentation</strong></a><strong> by Anna Lafontaines of EPRI on grid enhancing technologies:</strong></h5>
<ul>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Advanced connectors</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Dynamic line rating</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Advanced power flow controllers</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Transmission topology optimization</span></li>
</ul>
<h5><strong>Staff updates on committee briefs:</strong></h5>
<ul>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">60 ongoing projects</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Detailed </span><a href="https://ercot-control-docs.s3.us-west-2.amazonaws.com/12/5-2-real-time-co-optimization-implementation-update.pdf"><span style="font-weight: 400;">update</span></a><span style="font-weight: 400;"> on Real Time Co-Optimization (RTC)</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Discussion of risks associated with changes to RTC methodology</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Emphasis on following NPRR process for future enhancements</span></li>
</ul>
<h5><strong>Grid transformation initiatives </strong><a href="https://ercot-control-docs.s3.us-west-2.amazonaws.com/12/5-3-grid-transformation-initiatives-update.pdf"><strong>update</strong></a><strong>:</strong></h5>
<ul>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Discussion on tiered load categories</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Discussion on definitions of loads</span></li>
</ul>
<p><span style="font-weight: 400;">Technology and Security Committee Meeting available for </span><a href="/pages/calendar/meeting/smart-agenda/?event_id=3325"><span style="font-weight: 400;">rebroadcast</span></a><span style="font-weight: 400;">.</span></p>
<p><a href="/sharing/?token=eb5811aa-b02b-467c-91ab-b67108a673d4"><span style="font-weight: 400;">12</span></a><span style="font-weight: 400;"> - Other Business Discussion - Vice Chair - Bill Flores</span></p>
<ul>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">No additional business was raised by board members.</span></li>
</ul>
<p><a href="/sharing/?token=719c95c8-51cd-4362-bbdc-72b3a2d7192d"><span style="font-weight: 400;">13</span></a><span style="font-weight: 400;"> - Vote on Matters from Executive Session Vote - Vice Chair</span></p>
<ul>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">General session recessed to reconvene after the executive session.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Bill Flores, vice chair of the ERCOT board of directors, reconvened the general session.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Motion to approve Baker Tilley as the 2024 ERCOT 401K savings plan auditor approved unanimously.</span></li>
<li style="font-weight: 400;" aria-level="1"><span style="font-weight: 400;">Motion to approve the litigation matter discussed in executive session under agenda item ES 3.5 approved unanimously.</span></li>
</ul>
<p><span style="font-weight: 400;">14 - Adjournment - Vice Chair - Bill Flores</span></p>