The Wilmer project is a tier one project in Dallas County with an estimated cost of $158 million and an in-service date of May 2026.
The project addresses reliability needs due to a new confirmed load of 756 MW.
Four project options were evaluated; options 1 and 4 were shortlisted.
Option 1 was chosen as the preferred solution due to results of the planned maintenance outage analysis, long-term load-serving capability assessment, and preliminary cost estimates
Detailed analyses like congestion, generation addition impact, load scaling, and SSR assessment showed option 1 is viable without adverse impacts.
ERCOT recommends option 1 with a total cost of approximately $158.2 million and requires a CCN.
Next steps include publishing the EIR report by the end of the week, presenting it to TAC in January, and seeking Board endorsement in February.
Oncor's Forney project is a Tier 1 initiative with an estimated $103.5 million cost, aiming for completion by December 1, 2025, to address post-contingency thermal overloads and aging infrastructure.
ERCOT identified thermal violations but no voltage violations during preliminary assessments.
Four options for the switch rebuild were considered: Option 1, 1A, 2, and 3, were shortlisted with Option 2 being deemed infeasible by Oncor.
Option 1A is the ERCOT preferred option due to addressing reliability violations and having the least cost.
Sensitivity analysis showed no significant impact from additional generation or load scaling on the project's necessity.
ERCOT's congestion and SSR assessments found no significant issues, and Option 1A's completion is scheduled for December 2025.
EIR posting is planned for December 2024, with recommendations to be presented in early 2025, seeking endorsement by February 2025.
▶️ 5 - EIR Status Update – Venus Switch to Sam Switch 345-kV Line Project - ERCOT
Project Overview: Southwest Houston 345-kV Reliability Project presented by Raja Kakarla from CenterPoint Energy.
CenterPoint Energy serves over 21 gigawatts in Houston with various tie-lines built in 2007 and 2018.
Increase of renewable generation along the 3.5 kV transmission lines from 5.5 gigawatts in 2018 to an expected 12.1 gigawatts by 2025.
Project needs identified due to high condition costs and congested elements in 2022 and 2023 studies.
Two reliability projects within CenterPoint energy footprint identified in 2023 RTP study.
Project Goals: Looping 345 kV Elmaton-W.A. Parish ckt 39 into Bailey substation; installing a 20 Ohm line reactor; reconductoring and rebuilding certain lines to relieve overloads.
Expected cost of the project is around $569,322,000, including minimizing outages during construction.
Project timeline: Construction to begin in 2025, service expected by summer peak of 2028.
No CCN applications required as the project uses existing right of way.
Public comment period ended November 4; independent review completion expected by Q1/Q2 2025.