Meeting Summary - 06/28/24 Permian Basin Reliability Plan Study Workshop

Grid Monitor Staff Writer
07/01/2024

1 - Antitrust Admonition - Robert Golen

2 - Miscellaneous Updates - ERCOT - Roberto Golen/Ying Li

3 - ERCOT Status Update – Permian Basin Reliability Plan Study & Next Steps - ERCOT

Key Points:
Next Steps:

4 - Q/A & Stakeholder Feedback - Robert Golen

Q/A & Stakeholder Feedback - Robert Golen

Summary:

Answer confirmed to fall under data center load.

Answer: Discussion on a state-wide plan to meet load growth.

Answer: Details on additional generation added to meet transmission needs.

Answer: Study reports confirmed to be posted once finalized.

Answer: No detail on bundle configuration yet, but it will be shared in the report. The study did not conduct a no solar case.

Answer: Confirmed consideration due to performance, but details and implementations remain to be explored.

Answer: Discussed variability based on TSP projections.

Answer: There is a way to meet the 2030 and 2038 load with the method presented. 

Answer: Local projects will address short-term needs whereas import paths cater to long-term growth.

 

Answer: The numbers the TSPs provided are applicable for both the 2030 and the 2038 case.

Answer: It wouldn’t have to go through the RPG process. 

Answer: If the commission wants to proceed better cost estimates will be worked on with the TSPs.

5 - Adjourn